Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

can someone solve this ?​
-5/12 x 5/8 help please
The sum of a number and 17 is twenty-two"?
Which statements can be used to describe a ray? (pick 2 answer choices)A) A part of a line B) Has two endpoints C) Has no dimension D) Has only one endpoint E)
how do you eat food?
does she invite you into passive​
Erin gets her exercise by running. The graph shows the distances she covers in a given amount of time. How many hours does it take for Erin to run 25 miles?
64×15=32×30 true or false
don’t know how to delete this, ignore it.
A certain element has only two naturally occurring isotopes: one with 18 neutrons and the other with 20 neutrons. The element forms 12 charged ions when in ioni