If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

estimate the line of best fit using two points on the line ​
Nikolai always strived to be a stern man. It was the most apparent in the way he managed to hide a half-smile when he thought something was genuinely funny. He
Help please find jkl, kjn, klj, klm.
What was one of Kublai Khan’s achievements? Kublai Khan captured the city of Baghdad. Kublai Khan united the tribes of Mongolia. Kublai Khan founded the Mongol
Does anyone know the answers?
Someone help me out
Need Help with the attached pic. Please show work. Thanks
Complete the statements and then calculate the change in consumption. The consumption function shows the relationship between consumption spending and The slope
Consider three scenarios in which a particular box moves downward under the pull of gravity : (A) In scenario A, the box falls straight down from an initial hei
A number divided by -8 is 7. As an equation