It takes 6 workers 8 hours to tile a hall . How long will it take 4 workers to complete the same job

Respuesta :

icandoitjwk icandoitjwk
  • 15-01-2022
6w=8
2w=8/3

So
4w=8/3x2
4w=16/3
Answer Link

Otras preguntas

7 people are running in a race. If we only care about first, second and third place, how many possible outcomes are there?
what does 4 minus 2/4 equals
What changes to landforms can ice cause?
what is the value of the dependent variable if the value is 0? f(x)=-13x2+5x-2x+8
Which describes one part of the Columbian Exchange? A. Potatoes and tomatoes were introduced in the Americas. B. People from Africa were brought to the Americas
While waiting at a bus stop, Jacinta looked up and noticed that she could not see the mountains because of a thick layer of smog. Where does Jacinta most likely
What country helped the colonists by giving them supplies, but also sent their navy to help fend off the British and protect port cities?
Write in powers of 10 notation: 3 trillion; five-thousandths; 730,000,000,000,000; 0.000000000082.
Which of the following best explains why the Chinese rebuilt the Great Wall in the 1400s? A. to keep out invaders from the Japanese islands B. to keep out Mongo
What can government do to reduce unemployment?