The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish" (FF).
a. True
b. False

Respuesta :

Limosa
Limosa Limosa
  • 15-01-2020

Answer:

Option B i.e., False is the correct option.

Explanation:

The following statement is incorrect because, It is the logical relationship not the logical dependency to recognize the series of the activity of the project details. So, that's why the following option is correct according to the given statement. the following relationship is also established between the specific schedule.

Answer Link

Otras preguntas

what number is 1,000,000 greater than 337,676
who can help me with quantitative observation examples
The part of cell division that causes the separation of the cytoplasm is _____? Mitosis,Meiosis,Cytokinesis
If sulfur 34 undergoes alpha decay, what will I become?
Solving linear equations is not for me :b i need to know p - 15 = 13 - 6p
Solving linear equations is not for me :b i need to know p - 15 = 13 - 6p
Chemical equation of photosynthesis?
what is the answer to 4/7 x - 3 =6
30% of a number is one-thirtieth of x, find the initial expression as a fraction of x
the speed at which at a certain computer can access the internet is 2 megabytes per second how fast is this in megabytes per hour