2018, the westgate construction company entered into a contract to construct a road for santa clara county for $10,000,000. the road was completed in 2020. information related to the contract is as follows: 2018 2019 2020 cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 estimated costs to complete as of year-end 5,256,000 2,628,000 0 billings during the year 2,170,000 2,502,000 5,328,000 cash collections during the year 1,885,000 2,600,000 5,515,000 westgate recognizes revenue over time according to percentage of completion.